Mansfield City Schools Tentative
Five Year Permanent Improvement Plan
| 2013-2014 |
|
| District
wide asphalt |
$25,000 |
| District
wide plumbing fixtures |
$10,000 |
| Malabar
phase 1windows |
$100,000 |
| Prospect
hallway floors |
$10,000 |
| Prospect
classroom floors |
$15,000 |
| Sherman
phase 2 roof |
$75,000 |
| Springmill
phase 2 roof |
$75,000 |
| Springmill
boiler replacement |
$120,000 |
| Woodland
paint gym and hallways |
$40,000 |
| Malabar
Mehock Bleachers |
$48,170 |
| Malabar
Mehock drainage/fence |
$25,000 |
| Malabar Pool Boiler |
$40,000 |
| Gunther
Mechanical Purchase Service |
$45,200 |
| Gardiner
Trane Purchase Service |
$40,000 |
| Dump
Truck Bed |
$18,000 |
| Delivery
Mail Truck |
$35,000 |
| Total |
$721,370 |
| |
|
| 2014-2015 |
|
| District
wide asphalt |
$25,000 |
| District
wide plumbing fixtures |
$10,000 |
| Hedges
paint gym |
$15,000 |
| Malabar
phase 2 windows |
$100,000 |
| Prospect
classroom flooring |
$25,000 |
| Sherman
phase 3 roof (roof completed) |
$75,000 |
| Sherman
paint gym |
$15,000 |
| Springmill
phase 3 roof (roof completed) |
$75,000 |
| Woodland boiler replacement |
$100,000 |
| Woodland paint classrooms |
$40,000 |
| Total |
$480,000 |
| |
|
| 2015-2016 |
|
| District
wide asphalt |
$25,000 |
| District
wide plumbing fixtures |
$10,000 |
| Malabar
phase 3 windows (windows complete) |
$100,000 |
| Newman
phase 1windows |
$100,000 |
| Prospect
phase 3 flooring (flooring complete) |
$25,000 |
| Raemelton
boiler replacement |
$75,000 |
| Raemelton
phase 1roof |
$75,000 |
| Sherman
paint hallways |
$40,000 |
| Total |
$450,000 |
| |
|
| 2016-2017 |
|
| District wide asphalt |
$25,000 |
| District wide plumbing
fixtures |
$10,000 |
| Brinkerhoff Spanish Immersion
phase 1windows |
$100,000 |
| Newman phase 2 windows
(windows complete) |
$100,000 |
| Raemelton phase 2 roof |
$75,000 |
| Sherman phase 3 paint
classrooms (complete) |
$25,000 |
| Springmill boiler replacement |
$60,000 |
| West Fifth boiler replacement |
$60,000 |
| Total |
$455,000 |
| |
|
| 2017-2018 |
|
| District wide asphalt |
$25,000 |
| District wide plumbing fixtures |
$10,000 |
| Brinkerhoff Spanish Immersion
boiler replacement |
$120,000 |
| Brinkerhoff Spanish
Immersion phase 2 windows |
$100,000 |
| Hedges phase 1 roof |
$75,000 |
| Hedges paint hallways |
$25,000 |
| Prospect paint hallways |
$15,000 |
| Raemelton phase 3 roof (roof
complete) |
$75,000 |
| Total |
$445,000 |